KUKL PID WORK PROGRESS

WORK PROGRESS SUMMARY
BDS: 49.94 km out of 60.6 km
DNI: 612.80 km out of 670 km

 Package: DNI 3 Primary

Khumaltar RVT to Talchikhel (Ring Road)
Today: 0 m To Date: 1625 m Total: 1860 m
Pipe Diameter: 900 mm

Talchikhel (Ring Road) to Mahalaxmi sthan
Today: 0 m To Date: 558 m Total: 600 m
Pipe Diameter: 600 mm

Mahalaxmi sthan to Thasikhel
Today: 0 m To Date: 260 m Total: 275 m
Pipe Diameter: 400 mm